Over 1956 housing units are still incomplete while some are in various stages of construction, yet the Gauteng Department of Human Settlement has spent over R1 billion on 17 unfinished housing projects across the province.
The beneficiaries of these housing projects are in dire need of dignified housing for their families and have been severely affected by the long wait.
Only 340 incomplete houses will be completed in the 2022/23 financial year as well as the technical assessment of 1114 houses to determine the amount of work that needs to be done and the timelines for completion.
This information was revealed by the Gauteng MEC for Human Settlements, Lebogang Maile, in a written reply to my questions tabled in the Gauteng Provincial Legislature (GPL).
According to MEC, the department has spent R1 371 625 382.09 of the R16 450 401 283.7 initial allocated budget for these housing projects.
This is extremely concerning as the department has spent over R1 billion while some of these projects have used up their initial budget and some have underspent or spent nothing at all on the projects. The 3H Tamboville Proper and Wattville projects have used their entire budgets, while 3O Tswelopele Ext 6/Winnie Mandela Park and SD Tudor Shaft (HAD) Kagiso Ext 13 projects have spent zero of their allocated budgets.
Despite this department not having a proper comprehensive plan to accommodate the beneficiaries of these unfinished housing projects, some of these projects are still at the beginning stages with only the preliminary assessments having been done.
The longer these housing structures remain incomplete, the more vulnerable they are to vandalism and illegal occupation which will cost the department more money to fix or rebuild and evict illegal occupants.
The DA demands that MEC Maile must get his ducks in a row and prioritise completing these unfinished housing projects. Some of the people who have been on the housing waiting list have passed away and left their children struggling without dignified housing. Their children will continue to be exposed to inhuman living conditions and there is no hope that they will ever receive houses.
We will be conducting oversight inspections of these unfinished housing projects to ascertain what needs to be done to speed up the completion process so that the rightful beneficiaries can be allocated.